Park Cam – Bozüyük Glass Bottle Production Plant (Phases 1 and 2): Complete Electrical, IT and Automation Works

Park Cam – Bozüyük Glass Bottle Production Plant (Phases 1 and 2): Complete Electrical, IT and Automation Works

Turnkey delivery of all MV/LV/IT and automation works of the facility.

Scope of Work

  • 34,500 V cells
  • 6,300 V cells
  • 8 × 4,000 kVA power transformers (34,500 V / 400 V)
  • 2 × 2,500 kVA power transformers (34,500 V / 6,300 V)
  • MV / LV compensation panels
  • 8 × transformer distribution panels
  • 19 × main distribution panels (ADP)
  • 162 × distribution panels
  • 50 × MCC
  • 450 km of power and low-current cable
  • Cable carrier systems
  • Siemens S7-300 PLC, 2 SCADA servers, 2 SCADA clients, 40,000 tags, 695 communicating field devices

Project Information

  • Client: Park Cam Sanayi ve Tic. A.Ş.
  • Job Description: Bozüyük Glass Bottle Production Plant (Phases 1 and 2): Complete Electrical, IT and Automation Works
  • Location: Bilecik
  • Date: 2014-2016