Water & WastewaterŞanlıurfa · 2022-2023
Fernas Construction – Siverek Drinking Water Treatment Plant: Complete Electrical and Automation Works

Turnkey delivery of all MV/LV/IT and automation works of the facility.
Scope of Work
- MV cells
- 3 × 1.600 kVA transformer
- 2 × diesel generators
- Main distribution (ADP) and MCC panels
- 50,000 m of power and control cable
- Schneider DCS, redundant SCADA server-client architecture, 22,000 tags
Project Information
- Client: Fernas İnşaat A.Ş.
- Job Description: Siverek Drinking Water Treatment Plant: Complete Electrical and Automation Works
- Location: Şanlıurfa
- Date: 2022-2023
Kategori:Water & Wastewater
Tüm Projelere DönBenzer Projeler

Kocaeli · 2025
İsmail Köprülü – DSİ İnebeyli Pumping Station Electrical and Automation Works

2022
DSİ Kuzova Pumping Station – Motor Cell Overhaul and MV Soft Starter Application

Şanlıurfa · 2022-2023
Fernas Construction – Siverek Drinking Water Treatment Plant: Electrical and Automation Works for 6 Lift Stations

Isparta · 2021
En-Ez Construction – DSİ Atabey Pumping Station: Electrical Contracting, Automation and Mechanical Works
Engineering Solutions
Contact our expert team for your industrial automation and engineering projects.
Get an Offer & Contact