OthersBilecik · 2014-2016
Park Cam – Bozüyük Glass Bottle Production Plant (Phases 1 and 2): Complete Electrical, IT and Automation Works

Turnkey delivery of all MV/LV/IT and automation works of the facility.
Scope of Work
- 34,500 V cells
- 6,300 V cells
- 8 × 4,000 kVA power transformers (34,500 V / 400 V)
- 2 × 2,500 kVA power transformers (34,500 V / 6,300 V)
- MV / LV compensation panels
- 8 × transformer distribution panels
- 19 × main distribution panels (ADP)
- 162 × distribution panels
- 50 × MCC
- 450 km of power and low-current cable
- Cable carrier systems
- Siemens S7-300 PLC, 2 SCADA servers, 2 SCADA clients, 40,000 tags, 695 communicating field devices
Project Information
- Client: Park Cam Sanayi ve Tic. A.Ş.
- Job Description: Bozüyük Glass Bottle Production Plant (Phases 1 and 2): Complete Electrical, IT and Automation Works
- Location: Bilecik
- Date: 2014-2016
Kategori:Others
Tüm Projelere DönBenzer Projeler

Ankara · 2025
Presidential Guard Regiment Command – Generator Synchronization and Energy Monitoring Automation Modernization

Ankara · 2023-2024
MKE Ammunition Factory – Electro-Mechanical and Automation Works for 5 Induction Heating Machines

Eskişehir · 2023
Haier Group Renta Home Appliances – Eskişehir Factory No. 3 Complete MV/LV Electrical and Automation Works

Eskişehir · 2022
Haier Group Renta Home Appliances – Eskişehir Factory No. 2 Complete MV/LV Electrical and Automation Works
Engineering Solutions